Construction Update 2/19/11

here’s where we are at:

Building permit is in hand. Scheduled start time Monday morning (2/21).
The sawcut will happen and then they will excavate, set the forms for the footings and install the rebar. The city is closed on Monday, so we already scheduled an inspection for Tuesday morning. As soon as the inspection takes place, we will call for cement.
The cement will have to set for a day, then the columns and beam can get installed. The final cement pour (to finished floor height) will take place the following day and we will clean up.
. Call me if you have any questions.

Paul